A $260M AI buildout will put 2,304 Nvidia B300 chips in one U.S. site

A 0M AI buildout will put 2,304 Nvidia B300 chips in one U.S. site

By Stock Titan
Publication Date: 2026-04-22 12:00:00





Axe Compute (NASDAQ:AGPU) signed a 36-month, ~$260 million enterprise contract to deploy a dedicated cluster of 2,304 NVIDIA B300 GPUs and AI-focused high-speed storage in a single U.S. Tier 3 data center. Deployment targets Q3 2026 with 4.8 MW of dedicated N+1 power and take-or-pay, prepaid billing.

The agreement is the largest in company history, provides long-dated revenue visibility, includes enterprise service levels and renewal options, and is structured to deliver dedicated, U.S.-based GPU capacity for training, fine-tuning, and high-throughput inference.


Loading…

Loading translation…

Table of Contents

Positive


  • Contract value: $260 million over 36 months

  • Hardware scale: 2,304 NVIDIA B300 GPUs

  • Power committed: 4.8 MW with N+1 redundancy

  • Deployment timeline: targeted Q3 2026

  • Contracted structure: take-or-pay with deposit and prepayment

  • Largest enterprise engagement in company history

Negative


  • Concentration: entire cluster in a single U.S. Tier 3 data center