By Nadia Dubois
Publication Date: 2026-11-06 08:51:00
IREN told investors on November 5, 2026 that some infrastructure deliveries for Microsoft ran late, according to a Reuters report carried on Fidelity. The AI data center operator blamed a Microsoft-requested network-design change and supplier timing, said the slip carries no financial penalties, and laid out roughly $15 billion of planned capital spending for the rest of its fiscal year.