DTE still expects approval for OpenAI, Oracle’s data center service, despite the delay

DTE still expects approval for OpenAI, Oracle’s data center service, despite the delay

By Jennifer Eberbach | jeberbach@mlive.com
Publication Date: 2025-12-06 15:49:00

SALINE TWP., MI – DTE Energy officials are still awaiting approval from state regulators Special contracts for the energy supplier This would be Michigan’s first hyperscale data center project in Saline Township.

DTE officials “anticipate approval on Dec. 18,” when the Michigan Public Service Commission (MPSC) next meets, according to a business update to investors released Friday.

That’s despite DTE’s previous warning that the entire deal to power the massive 2.2 million square foot facility could be off the table if the Public Service Commission does not grant expedited approval by Friday, December 5th. The utility is applying for an ex-parte, accelerated permit to cover 1.4 gigawatts of electricity needs the data center powered by ChatGPT developer OpenAI and cloud computing giant Oracle on about 250 acres of a 575-acre property on W. Michigan Avenue in the township south of Ann Arbor.

While the MPSC was expected to consider DTE’s request for an expedited permit for the power…