Most of the Cheyenne Planning Commission members backed parts of Microsoft’s sweeping 3,200-acre southside expansion plans Monday night during a marathon five-hour hearing. 

But only one part of the plan — assigning agricultural zoning to the 3,050-acre Highlands area if it is annexed — will reach the June 8 City Council meeting with a recommendation to approve.

The remaining items — future land-use and zoning map amendments for two parcels in the vicinity of Laramie Community College — failed to get the four “yes” votes required by state law to give the land-use changes a formal thumbs up from the planners.

With two of seven commissioners absent, and the chair voting only in case of a tie, a single “no” was enough to flip majority support for the Highlands-related measures into a recommendation to deny. 

A majority, meanwhile, voted to outright deny changes for the nearby Read Property, which is already inside city limits.

That meant the future land-use map…