Amazon is racing to secure AI hardware earlier than before, even as data center power shortages leave some GPU systems waiting in warehouses.
Under a new Early Rack Receipt process, AWS expected to receive roughly $5 billion in Nvidia’s GB300 server racks at US facilities before final deployment, according to August internal emails reviewed by Business Insider. The company projected roughly $3 billion more in GB300 racks each month “for the foreseeable future,” one of the emails said.
Some AWS sites had room for more racks but not enough available power to turn them on, people familiar with the effort said, leaving finished equipment to be staged at intermediary warehouses until the facilities were ready.
At least one AWS team did not have “a clear forecasted path” for getting the incoming racks into data centers at the time, according to one of the emails.
Dark GPUs
A lack of new electricity capacity is one of several bottlenecks slowing the…